A post-tension slab is a stressed structure. Cutting a cable is not a drilling mistake, it is a structural event: the tendon loses prestress, the slab can deflect, and the repair is an engineered solution, not a patch.
| Item | Detected by GPR / cover meter? |
|---|---|
| Tendon | Usually, as a linear indication |
| Grout duct | Sometimes; duct may read as void |
| Sheared or displaced tendon | Poorly; layout may not match drawings |
| Edge stressing anchor | Only if within scan depth |
That last row is the one that causes incidents: a tendon displaced during a previous pour is not where the drawing says. Treat every scan as advisory and keep the clearance generous.
The scan is the only step that makes drilling near tendons safe, and different tools answer different questions. Using a rebar locator to find tendons is the single most common mistake on post-tensioned slabs.
| Tool | What it finds | What it misses | Use it for |
|---|---|---|---|
| Cover meter | Rebar depth and spacing | Tendons, plastic ducts | Establishing cover before a GPR pass |
| GPR (ground-penetrating radar) | Ducts, tendons, conduits, voids | Small diameter, deep targets | Locating tendon lines before marking |
| X-ray / radiography | Dense steel and tendon profile | Requires access both sides, safety controls | Confirmation where GPR is ambiguous |
GPR on a slab with a mesh and a duct grid produces a picture, not a coordinate. Mark the tendon lines on the surface in chalk, then treat every line as a no-drill band rather than a line: the duct has width, and the strand can sit off-centre inside it.
If a duct is hit, stop, do not backfill, and call the engineer. A grouted duct that has been breached can sometimes be injected and re-tensioned; a duct filled with concrete from a hurried repair usually cannot.
Holes near tendons are the ones an engineer will be asked about years later, so the file has to answer three questions without a site visit: where exactly the hole went, what was found during the scan, and who approved the proximity.
That record takes ten minutes at the rig and settles a dispute that otherwise costs a day of drilling and a structural review.
Striking a tendon is rare but it is not a situation to improvise. What happens in the first ten minutes decides whether it stays a repair or becomes an incident report.
The commercial point: the cost of a struck tendon is almost never the repair. It is the delay, the engineer's report and the loss of confidence, all of which are reduced by a clean record and an immediate stop.
Options in order of preference: relocate the penetration, reduce the core diameter, use a sleeved penetration cast during a later pour, or get a designed opening with supplementary reinforcement. Coring through a band is a decision for the engineer, not the driller.