Core drilling slurry is concrete fines suspended in water, and it is the part of the job most likely to cause a complaint, a blocked drain or a fine. The volume is small, but handling rules are not optional, and the cheapest plan is decided before the first hole.
| Hole | Slurry, roughly | Handling |
|---|---|---|
| 50 mm × 100 mm | 1-2 litres | Bucket |
| 100 mm × 200 mm | 6-10 litres | Tray |
| 150 mm × 300 mm | 20-30 litres | Drum or wet vacuum |
| 200 mm × 400 mm | 50-70 litres | Plan disposal before drilling |
Let the bucket stand for a few hours: solids settle and clear water sits on top. Decant the clear water, which in most jurisdictions may go to sanitary sewer with approval but never to storm drains, and put the solids in a skip as construction waste. Never pour slurry into a storm drain, a garden or a watercourse: it sets like weak concrete and it is the fastest route to a fine.
Slurry looks like a small stream and behaves like a large volume. Estimating it before the first hole decides whether you need a bucket, a settling tank or a vacuum truck.
| Hole | Concrete removed | Water used | Slurry to handle |
|---|---|---|---|
| 50 mm x 150 mm | 0.3 l | 2-4 l | 3-5 l |
| 100 mm x 300 mm | 2.4 l | 15-25 l | 18-28 l |
| 200 mm x 300 mm | 9.4 l | 40-60 l | 50-70 l |
| 300 mm x 400 mm | 28 l | 90-140 l | 120-170 l |
The removed concrete is trivial; the water is the problem. A single 200 mm hole can fill a standard wet vacuum twice, which is why containment has to be sized to the hole and not to the hose.
The settling container is the cheapest piece of equipment on the job and the one that decides whether disposal is legal. Skips and drums are fine; a hose into the site drain is not, and the fine is usually larger than the whole drilling contract.
Discharge rules vary by jurisdiction, but the logic is consistent: water that has passed through a settling stage and a filter, with pH near neutral and no visible solids, may go to a foul sewer with consent; water with cementitious solids may not go to surface water or storm drainage anywhere.
Slurry handling is judged by what is visible at the end of the day, not by the method statement. Four things on site decide whether the job reads as professional or as a mess that will not be repeated.
None of this is heavy equipment. It is one drum with a lid, one hose that gets wound up, and one line in the handover document — the three things most often missing when slurry becomes a complaint.
Ask the site manager where slurry is allowed before you start, write it into the method statement, and photograph the containment. Where the site runs waste transfer notes, put slurry solids on them. Asking costs nothing and is the only defence when a drain blocks three floors down.